Type of Item | INSTALLATION OF COMPLETE BOILER HEADER SH2 |
---|---|
Client | TIRRENO POWER |
End User | TIRRENO POWER |
Year of production | 2007 |
Project | BOILER REVAMPING |
Scope of supply | COMPLETE REVAMPING & INSTALLATION |
Note | Manufacturing and installation of the complete boiler main header SH2 at the Tirreno Power plant in Vado Ligure. Workforce involved 250 people Nr. of site welds about 26000 |