POWER

SUBSTITUTION OF MAIN BOILER LINES

Type of ItemSUBSTITUTION OF MAIN BOILER LINES
Final destinationItaly
Year of production2011
ProjectREVAMPING OF BOILER MAIN STEAM LINES
Scope of SupplyDESIGN, SUPPLY, WELDING, TESTING, START UP OF BOILER LINES
NoteDesign, site assembly, welding, and testing of the new elbow of the main boiler steam lines. 
Material A335 P22.
O.D. 609,6 mm thk. 42 mm.

Related Services

INSTALLATION OF COMPLETE BOILER HEADER SH2

POWER PLANT DUST SUPPRESSION SYSTEM

THERMO-ELECTRIC PLANT